The Energy Consulting GroupBusiness strategy for upstream oil and gas producers and service companies |
|||||
Our focus is to develop and
implement strategies that are practical, sustainable and allow
organizations to achieve their full potential. Our consultants have
long histories of working closely with senior executive teams of
firms of all sizes to help their companies not only be successful,
but achieve performance that stands out relative to
peers.
.
Contact Bill at
insight@energy-cg.com to find out how
we can help you.
|
|||||
Fracking a Nonconventional Oil Well In The Permian's Midland Basin Example Well: 50 frac stages over a 7500' horizontal lateral
Day 1:
06:00 15:00 9.00 RIG UP/DOWN LOC MIRU frac equipment, crane, ELU, grease
package, S3 pump down pumps, and Colt test pump. Pressure test
lubricator and S3 lines to 9,500 psi. Good test. Test iron to 9,500 psi.
Good test.
Day 2:
06:00 13:00 7.00 WAITING ON EQUIP/TOOLS WOT WAIT ON CTU 13:00 18:00 5.00 RIG UP/DOWN LOC MIRU 2” CTU and
crane. MU BHA #1 as follows: 4.65" mill, 3.75” crossover, 2.88"motor,
2.88 agitator, 2.88” hyd. disconnect, 2.88” bi-directional jar,2.88”
backpressure valve, 2.88” coil tubing connector. Surface test motor.
Good test. 18:00 05:00 11.00 WASH SAND/FILL REAM NU CT stack
and test to 9,500 psi. Good test. SICP 400 psi. RIH pumping 3.8 bpm at
6,600 psi returning 3.7 bpm at 300 psi on manifold. Tag RSI sleeve @
16,185’ (CTM). Pump 10 bbl dyed sweep, 10 bbl spacer and final 10 bbl
dyed sweep. Circulate well clean with a trace of sand in the returns.
POOH. 05:00 06:00 1.00 PU/LD BHA TRP LD BHA #1 06:00 12:00 6.00 FRACTURE STIM CPOOH with
BHA #1.
Perform injection test.pump 285 bbls at 40 bpm and 8,488 psi. 12:00 18:00 6.00 TCP PERF LD BHA #1. MU and RIH
with TCP guns to 16,202’ CTM (RSI at 16,171’). PU and perf stage #1 from
16,143’ to 16,021’. POOH and break out TCP guns. Purge coil with N2.
RDMO CTU. Frac stage #2. Plug/perf and frac stage #3 thru #xx
18:00 20:15 2.25 FRACTURE STIM FRAC STAGE #2 AVG RATE = 71 BPM AVG PSI = 6,377 PSI TOTAL FLUID = 4,904 BBLS TOTAL SAND = 173,781 LBS
20:15 22:15 2.00 WL PERFORATE PERF PERFORATESTAGE #3 PERFORATIONS; 15.873' - 15,991'
22:15 00:30 2.25 FRACTURE STIM FRAC STAGE #3 AVG RATE = 70 BPM AVG PSI = 6,083 PSI TOTAL FLUID = 4,773 BBLS TOTAL SAND = 206,083 LBS
00:30 00:30 WL PERFORATE PERF PERFORATESTAGE #4 :PERFORATIONS: 15,724' - 15,841'
00:30 00:30 FRACTURE STIM FRAC STAGE #4 AVG RATE = 70 BPM AVG PSI = 4,857 PSI TOTAL FLUID = XXXXBBLS TOTAL SAND = 209,147 LBS 00:30 00:30
WL PERFORATE PERF PERFORATESTAGE #5 PERFORATIONS: 15,574' - 15,692'
Day 3:
06:00 08:00 2.00 FRACTURE STIM FRAC STAGE #5 AVG RATE = 70 BPM AVG PSI = 4,487 PSI TOTAL FLUID = 4402 BBLS TOTAL SAND =208,227 LBS 08:00 10:00
2.00 WL PERFORATE PERF PERFORATESTAGE #6 PERFORATIONS = 15,422' - 15,544'
10:00 12:00 2.00 FRACTURE STIM FRAC STAGE #6 AVG RATE = 70 BPM AVG PSI = 4,374 PSI TOTAL FLUID = 4,426BBLS TOTAL SAND = 211,033 LBS 12:00 14:00
2.00 WL PERFORATE PERF PERFORATESTAGE #7 PERFORATIONS = 15,272' - 15,394'
14:00 16:00 2.00 FRACTURE STIM FRAC STAGE #7 AVG RATE = 70 BPM AVG PSI = 4,902 PSI TOTAL FLUID = 4,811BBLS TOTAL SAND =208,504 LBS 16:00 18:00 2.00 MISCELLANEOUS OTH Waiting on Key
Personnel 18:00 20:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 8 PERFORATIONS = 15,123' - 15,244' 20:00 21:30 1.50 FRACTURE
STIM FRAC STAGE # 8 AVG RATE = 62 BPM AVG PSI = 4,656 PSI TOTAL FLUID = XXXX8BBLS TOTAL SAND =210,524 LBS 21:30 23:00
1.50 WL PERFORATE PERF PERFORATESTAGE # 9 PERFORATIONS = 14,973' - 15,095'
23:00 00:30 1.50 FRACTURE STIM FRAC STAGE # 9 AVG RATE = 60 BPM AVG PSI = 4,820 PSI TOTAL FLUID = 4,649BBLS TOTAL SAND =208,806 LBS 00:30 02:30
2.00 WL PERFORATE PERF PERFORATESTAGE # 10 PERFORATIONS = 14,823' - 14,945'
02:30 04:15 1.75 FRACTURE STIM FRAC STAGE # 10 AVG RATE = 62 BPM AVG PSI = 4,879 PSI TOTAL FLUID = 4,620BBLS TOTAL SAND =210,227 LBS 04:15 06:00
1.75 WL PERFORATE PERF PERFORATESTAGE # 11 PERFORATIONS = 14,673' - 14,795'
Day 3:
06:00 06:00 FRACTURE STIM FRAC STAGE # 11 AVG RATE = 70 BPM AVG PSI = 4,923 PSI TOTAL FLUID = 4,739 BBLS TOTAL SAND =208,740 LBS 06:00 09:00
3.00 WL PERFORATE PERF PERFORATESTAGE # 12 PERFORATIONS = 14,523' - 14,645'
09:00 12:00 3.00 FRACTURE STIM FRAC STAGE # 12 AVG RATE = 70 BPM AVG PSI = 4,968 PSI TOTAL FLUID = 4,688BBLS TOTAL SAND =208,540 LBS 12:00 14:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 13 PERFORATIONS = 14,374' - 14,495'
14:00 16:00 2.00 FRACTURE STIM FRAC STAGE # 13 AVG RATE = 70 BPM AVG PSI = 4,665 PSI TOTAL FLUID = 4,722BBLS TOTAL SAND = 210,415 LBS 16:00 18:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 14 PERFORATIONS = 14,224' - 14,346'
18:00 20:00 2.00 FRACTURE STIM FRAC STAGE # 14 AVG RATE = 70 BPM AVG PSI = 5,090 PSI TOTAL FLUID = 5,366BBLS TOTAL SAND = 202,914 LBS 20:00 22:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 15 PERFORATIONS = 14,074' - 14,196'
22:00 00:00 2.00 FRACTURE STIM FRAC STAGE # 15 AVG RATE = 70 BPM AVG PSI = 5,101 PSI TOTAL FLUID = 5,195BBLS TOTAL SAND = 209,910 LBS 00:00 01:30
1.50 WL PERFORATE PERF PERFORATESTAGE # 16 PERFORATIONS = 13,924' - 14,046 01:30 03:00 1.50 FRACTURE
STIM FRAC STAGE # 16 AVG RATE = XX BPM AVG PSI = XXXX PSI TOTAL FLUID = XXXXBBLS TOTAL SAND =XXXXXX LBS 03:00 04:30
1.50 WL PERFORATE PERF PERFORATESTAGE # 17 PERFORATIONS = 13,775' - 13
Day 4:
04:30 07:30 1.50 FRACTURE STIM FRAC STAGE # 17 AVG RATE = 70 BPM AVG PSI = 4,352 PSI TOTAL FLUID = 4,577BBLS TOTAL SAND = 208,031 LBS 07:30 09:30
2.00 WL PERFORATE PERF PERFORATESTAGE # 18 PERFORATIONS = 13,625' - 13,747'
09:30 11:30 2.00 FRACTURE STIM FRAC STAGE # 18 AVG RATE = 70 BPM AVG PSI = 4,748 PSI TOTAL FLUID = 5,052BBLS TOTAL SAND =209,293 LBS 11:30 13:30
2.00 WL PERFORATE PERF PERFORATESTAGE # 19 PERFORATIONS = 13,475' - 13,597'
13:30 15:30 2.00 FRACTURE STIM FRAC STAGE # 19 AVG RATE = 70 BPM AVG PSI = 4,542 PSI TOTAL FLUID = 4,705BBLS TOTAL SAND =208,079 LBS 15:30 17:00
1.50 WL PERFORATE PERF PERFORATESTAGE # 20 PERFORATIONS = 13,325' - 13,447'
17:00 18:45 1.75 FRACTURE STIM FRAC STAGE # 20 AVG RATE = 62 BPM AVG PSI = 4,885 PSI TOTAL FLUID = 4,551 BBLS TOTAL SAND = 204,908 LBS 18:45 20:30
1.75 WL PERFORATE PERF PERFORATESTAGE # 21 PERFORATIONS = 13,175' - 13,297'
20:30 22:30 2.00 FRACTURE STIM FRAC STAGE # 21 AVG RATE = 62 BPM AVG PSI = 4,437 PSI TOTAL FLUID = 4,555BBLS TOTAL SAND = 209,430 LBS 22:30 00:30
2.00 WL PERFORATE PERF PERFORATESTAGE # 22 PERFORATIONS = 13,026' - 13,147'
00:30 02:15 1.75 FRACTURE STIM FRAC STAGE # 22 AVG RATE = 62 BPM AVG PSI = 4,672 PSI TOTAL FLUID = 4,516 BBLS TOTAL SAND = 208,947 LBS 02:15 04:00
1.75 WL PERFORATE PERF PERFORATESTAGE # 23 PERFORATIONS = 12,876' - 12,988'
04:00 06:00 2.00 FRACTURE STIM FRAC STAGE # 23 AVG RATE = 70 BPM AVG PSI = 4,804 PSI TOTAL FLUID = 4,559 BBLS TOTAL SAND = 210,087 LBS
Day 5:
06:00 07:30 1.50 WL PERFORATE PERF PERFORATESTAGE # 24 PERFORATIONS = 12,726' - 12,848'
07:30 09:30 2.00 FRACTURE STIM FRAC STAGE # 24 AVG RATE = 70 BPM AVG PSI = 4,588 PSI TOTAL FLUID = 4,617BBLS TOTAL SAND = 209,651 LBS 09:30 12:00
2.50 WL PERFORATE PERF PERFORATESTAGE # 25 PERFORATIONS = 12,576' - 12,698'
12:00 14:00 2.00 FRACTURE STIM FRAC STAGE # 25 AVG RATE = 70 BPM AVG PSI = 4,363 PSI TOTAL FLUID = 4,558BBLS TOTAL SAND = 210,060 LBS 14:00 16:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 26 PERFORATIONS = 12,427' - 12,548'
16:00 18:00 2.00 FRACTURE STIM FRAC STAGE # 26 AVG RATE = 70 BPM AVG PSI = 4,270 PSI TOTAL FLUID = 4463 BBLS TOTAL SAND = 209,001 LBS 18:00 20:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 27 PERFORATIONS = 12,277' - 12,399'
20:00 22:00 2.00 FRACTURE STIM FRAC STAGE # 27 AVG RATE = 70 BPM AVG PSI = 4,484 PSI TOTAL FLUID = 4,801BBLS TOTAL SAND = 208,835 LBS 22:00 00:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 28 PERFORATIONS = 12,127' - 12,249'
00:00 02:00 2.00 FRACTURE STIM FRAC STAGE # 28 AVG RATE = 70 BPM AVG PSI = 4,159 PSI TOTAL FLUID = 4,701BBLS TOTAL SAND = 209,283 LBS 02:00 04:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 29 PERFORATIONS = 11,977' - 12,099'
04:00 06:00 2.00 FRACTURE STIM FRAC STAGE # 29 AVG RATE = 70 BPM AVG PSI = 4,593 PSI TOTAL FLUID = 4,588BBLS TOTAL SAND = 211,002 LBS
Day 6: 06:00
07:30 1.50 WL PERFORATE PERF PERFORATESTAGE # 30 PERFORATIONS = 11,828' - 11,949'
07:30 08:45 1.25 FRACTURE STIM FRAC STAGE # 30 AVG RATE = 70 BPM AVG PSI = 4,884PSI TOTAL FLUID = 4,502BBLS TOTAL SAND = 211,630 LBS 08:45 10:45
2.00 WL PERFORATE PERF PERFORATESTAGE # 31 PERFORATIONS = 11,678' - 11,800'
10:45 12:00 1.25 FRACTURE STIM FRAC STAGE # 31 AVG RATE = 70 BPM AVG PSI = 4,220 PSI TOTAL FLUID = 4,488BBLS TOTAL SAND = 209,136 LBS 12:00 14:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 32 PERFORATIONS = 11,528' - 11,650' 14:00 15:15
1.25 FRACTURE STIM FRAC STAGE # 32 AVG RATE = 70 BPM AVG PSI = 4,001 PSI TOTAL FLUID = 4,399BBLS TOTAL SAND = 209,401 LBS 15:15 17:15
2.00 WL PERFORATE PERF PERFORATESTAGE # 33 PERFORATIONS = 11,378' - 11,500'
17:15 19:00 1.75 FRACTURE STIM FRAC STAGE # 33 AVG RATE = 59 BPM AVG PSI = 4,141 PSI TOTAL FLUID = 4,572BBLS TOTAL SAND = 207,627 LBS 19:00 20:45
1.75 WL PERFORATE PERF PERFORATESTAGE # 34 PERFORATIONS = 11,228' - 11,350'
20:45 22:30 1.75 FRACTURE STIM FRAC STAGE # 34 AVG RATE = 61 BPM AVG PSI = 4,226 PSI TOTAL FLUID = 4,543 BBLS TOTAL SAND = 211,551 LBS 22:30 00:15
1.75 WL PERFORATE PERF PERFORATESTAGE # 35 PERFORATIONS = 11,079' - 11,200'
00:15 02:00 1.75 FRACTURE STIM FRAC STAGE # 35 AVG RATE = 61 BPM AVG PSI = 4,246 PSI TOTAL FLUID = 4,549BBLS TOTAL SAND = 211,163 LBS 02:00 03:30
1.50 WL PERFORATE PERF PERFORATESTAGE # 36 PERFORATIONS = 10,929' - 11
03:30 06:00 2.50 FRACTURE STIM FRAC STAGE # 36 AVG RATE = 70 BPM AVG PSI = 4,488 PSI TOTAL FLUID = XXXXBBLS TOTAL SAND = 208,508 LBS
Day 7: 06:00
08:15 2.25 WL PERFORATE PERF PERFORATESTAGE # 37 PERFORATIONS = 10,779' - 10,901'
08:15 10:15 2.00 FRACTURE STIM FRAC STAGE # 37 AVG RATE = 70 BPM AVG PSI = 4,268 PSI TOTAL FLUID = 4,367 BBLS TOTAL SAND = 209,836 LBS 10:15 12:15
2.00 WL PERFORATE PERF PERFORATESTAGE # 38 PERFORATIONS = 10,629' - 10,751'
12:15 14:15 2.00 FRACTURE STIM FRAC STAGE # 38 AVG RATE = 71 BPM AVG PSI = 4,075 PSI TOTAL FLUID = 4,417BBLS TOTAL SAND = 212,640 LBS 14:15 16:15
2.00 WL PERFORATE PERF PERFORATESTAGE # 39 PERFORATIONS = 10,480' - 10,601'
16:15 18:45 2.50 FRACTURE STIM FRAC STAGE # 39 AVG RATE = 60 BPM AVG PSI = 3,846 PSI TOTAL FLUID = 4,376 BBLS TOTAL SAND = 208,781 LBS 18:45 21:15
2.50 WL PERFORATE PERF PERFORATESTAGE # 40 PERFORATIONS = 10,330' - 10,452'
21:15 23:00 1.75 FRACTURE STIM FRAC STAGE # 40 AVG RATE = 70 BPM AVG PSI = 4,420 PSI TOTAL FLUID = 4,487BBLS TOTAL SAND = 210,090 LBS 23:00 01:00
2.00 WL PERFORATE PERF PERFORATESTAGE # 41 PERFORATIONS = 10,180' - 10,302'
01:00 02:45 1.75 FRACTURE STIM FRAC STAGE # 41 AVG RATE = 70 BPM AVG PSI = 4,222 PSI TOTAL FLUID = 4,562 BBLS TOTAL SAND = 208,407 LBS 02:45 04:30
1.75 WL PERFORATE PERF PERFORATESTAGE # 42 PERFORATIONS = 10,030' - 10,150'
04:30 06:00 1.50 FRACTURE STIM FRAC STAGE # 42 AVG RATE = 70 BPM AVG PSI = 6,194 PSI TOTAL FLUID = 4,479BBLS TOTAL SAND = 210,396 LBS
Day 8: 06:00
07:30 1.50 WL PERFORATE PERF PERFORATESTAGE # 43 PERFORATIONS = 9,880' - 10,002'
07:30 08:45 1.25 FRACTURE STIM FRAC STAGE # 43 AVG RATE = 70 BPM AVG PSI = 4,268 PSI TOTAL FLUID = 4,359BBLS TOTAL SAND = 210,331 LBS 08:45 10:15
1.50 WL PERFORATE PERF PERFORATESTAGE # 44 PERFORATIONS = 9,731' - 9,852'
10:15 11:30 1.25 FRACTURE STIM FRAC STAGE # 44 AVG RATE = 70 BPM AVG PSI = 4,194 PSI TOTAL FLUID = 4,356BBLS TOTAL SAND = 208,854 LBS 11:30 13:00
1.50 WL PERFORATE PERF PERFORATESTAGE # 45 PERFORATIONS = 9,581' - 9,703'
13:00 14:15 1.25 FRACTURE STIM FRAC STAGE # 45 AVG RATE = 70 BPM AVG PSI = X4,240 PSI TOTAL FLUID = 4,303BBLS TOTAL SAND = 209,806 LBS 14:15 15:30
1.25 WL PERFORATE PERF PERFORATESTAGE # 46 PERFORATIONS = 9,431' - 9,553'
15:30 16:45 1.25 FRACTURE STIM FRAC STAGE # 46 AVG RATE = 68 BPM AVG PSI = 4,149 PSI TOTAL FLUID = 4,509 BBLS TOTAL SAND = 210,672 LBS 16:45 18:00
1.25 WL PERFORATE PERF PERFORATESTAGE # 47 PERFORATIONS = 9,281' - 9,403'
18:00 19:30 1.50 FRACTURE STIM FRAC STAGE # 47 AVG RATE = 58 BPM AVG PSI = 3,858 PSI TOTAL FLUID = 4,559 BBLS TOTAL SAND = 209,751 LBS 19:30 20:45
1.25 WL PERFORATE PERF PERFORATESTAGE # 48 PERFORATIONS = 9,132' - 9,253
20:45 22:00 1.25 FRACTURE STIM FRAC STAGE # 48 AVG RATE = 60 BPM AVG PSI = 3,425 PSI TOTAL FLUID = 4,450 BBLS TOTAL SAND = 208,468 LBS 22:00 23:30
1.50 WL PERFORATE PERF PERFORATESTAGE # 49 PERFORATIONS = 8,982' - 9,104'
23:30 01:00 1.50 FRACTURE STIM FRAC STAGE # 49 AVG RATE = 61 BPM AVG PSI = 3,776 PSI TOTAL FLUID = 4,603BBLS TOTAL SAND = 211,020 LBS 01:00 02:30
1.50 WL PERFORATE PERF PERFORATESTAGE # 50 PERFORATIONS = 8,832' - 8,954'
02:30 04:00 1.50 FRACTURE STIM FRAC STAGE # 50 AVG RATE = 61 BPM AVG PSI = 3,735 PSI TOTAL FLUID = 4,518 BBLS TOTAL SAND = 208,998 LBS 04:00 06:00 2.00 OTHER WL WORK LOG Set kill plug at
9,'. POOH and bleed pressure to zero. SIW and secure.
Day 9:
06:00 06:00 24.00 RIG UP/DOWN LOC RDMO Frac, ELU, crane, grease package,
Copumps, water treatment, and water transfer. ND frac s bottom master
valve). NU 5 1/8” 10K x 4” flowcross on top of bottom valve. Go to The Energy Consulting Group home page for more oil and gas related information. |
|
||||
|
|
||||