These projects were notable for
being fast tracked and not normally manned designs. From the last
delineation well to first gas was less than two and a half years,
which included gas contract negotiations, project justification,
contracting, design, construction, installation and commissioning.
Also, these large facilities extended a trend which ARCO British
pioneered of demanning facilities. Despite being complex
installations with a full suite of processing kit, including
water/gas/condensate separation, hydrate and corrosion inhibition
systems, compression, etc., these installations were designed to be
remotely operated from a shore base over 100 miles away.
.........................Source: SLP
Engineering
Bill and his team team were
responsible for:
-
supporting and evaluating exploration/delineation
drilling efforts, including well justifications and approvals,
support while drilling and supervising/evaluating well tests
-
preparing the plan of development (POD),
including the size and type of platforms, processing required
(water separation, dehydration, glycol injection and retrieval,
compression, etc.), number of wells and their design, well
locations, pipeline options, etc.)
-
assessing health, safety and environmental
aspects of the project
-
building and using reservoir simulation models to
assist with the POD preparation and to build life of field
investment profiles
-
assisting gas contract negotiations
-
developing the capital and operating cost
estimates, production profiles, and economics for use in the
Authorization of Expenditure (AFE)
-
preparing the Authorization for Expenditure
(AFE)
-
coordinating the approval process through ARCO
British Ltd and ARCO corporate HQ
-
serving as project coordinators by aligning the
efforts of personnel from major projects, operations, geoscience,
etc. as the project moved into active development
|